Tips and Techniques For Pouring Self-Leveling Underlayment

We’ll show you the step-by-step process to achieve a perfectly flat and level underlayment that’s smooth as glass.

Our editors and experts handpick every product we feature. We may earn a commission from your purchases.
Learn more.

Any time you install a new floor covering, you need a level subfloor, and most aren’t level (at least not completely). That’s where self-leveling underlayment comes in. It’s a thin cementitious mixture that spreads out when you apply it to find its own level—hence the name.

Self-leveling underlayment is a must under any floor covering, particularly a thin one like linoleum or vinyl, but it’s especially useful for embedding radiant heating pipes or wires. However, we aren’t necessarily suggesting you should DIY in-floor heat. Shelley Nytes, who manages a plumbing and heating service, explains why it may not be a good idea: “There are numerous codes to follow regarding the length of runs, materials used for PEX piping, the manifold setups, how it hooks up to a pump, the type of liquid used in the pex runs, etc. It all has to be pressure tested as well. There are also situations where in basements you have to have this in before the concrete is poured.”

Here we show you how we poured self-leveling underlayment during an in-floor heating installation that we did, but you can apply our technique to any other type of floor covering installation.

1 / 17

Pouring Self-Leveling Underlayment Over Electric Cables | Construction Pro Tips
FAMILY HANDYMAN

The Right Floor Leveler Choice for in-Floor Heat

Self-leveling underlayment is a great choice under any tiled floor, but it’s the absolute best choice when installing tile over an in-floor heating system. Installing cement board won’t work, and if you choose to lay down a mortar bed it takes longer, it’s harder to achieve an even surface, and the screeding process can damage the heating cables or mats.

Interior designer  Rosa Santiago Zimmerman comments: “As a general contractor, we utilize self-leveling underlayment on a variety of substrates, including concrete, tile, exterior-grade plywood, and oriented strand board (OSB). This material is essential for achieving a smooth, level surface in preparation for the installation of finish flooring such as tile, hardwood, laminate, carpet, or vinyl. Its use ensures a high-quality, durable, and long-lasting flooring system.”

2 / 17

Cleaning the floor before pouring self-leveler | Construction Pro Tips
FAMILY HANDYMAN

Clean the Floor

Thoroughly sweep and vacuum the entire floor. The floor needs to be primed before adding the floor leveler and you’ll want the primer to soak into the floor, not the dirt and dust sitting on top of it. Keep a marker or roll of tape in your pocket while you’re vacuuming, and mark all the holes or cracks in the wood that will need to be sealed up.

3 / 17

Taping over the seams before pouring | Construction Pro Tips
FAMILY HANDYMAN

Caulk and Tape Over Holes and Seams

If the liquid leveler is not totally contained, you will end up with a big mess on your hands and probably have to re-pour the floor leveler. Seal all holes and seams in the plywood with caulk. The leveler will drain through an opening as small as a nail hole, so be thorough. A good choice for filling those holes and cracks is the type of caulk that goes on white but turns clear when it dries, because you can tell when it is done setting up.

Taping over the caulk isn’t required, but it’s a terrific way to avoid stepping in a glob and tracking it around the rest of the house. When working on an older house with floor planks instead of plywood, cover the whole floor in self-adhering roofing underlayment. Looking for more ideas?

Check out the benefits of synthetic roofing underlayment over asphalt felts.

4 / 17

Installing sill sealer at the walls | Construction Pro Tips
FAMILY HANDYMAN

Install Sill Sealer At the Walls

Sill sealer is a foam gasket that framers use to seal the connection between a foundation and the bottom wall plate. Sill sealer also makes a great barrier to keep the liquid underlayment from escaping into other rooms or into the basement on exterior walls. Hold it in place with staples. Keep the staples low enough so the staple holes will be hidden by the base trim. Your options are likely either 3-1/2-in. or 5-1/2-in. A wide sill sealer will work, but the taller it is, the more protection it provides painted walls from floor-level splashes.

5 / 17

Caulk the sill sealer at the floor line along the walls | Construction Pro Tips
FAMILY HANDYMAN

Caulk the Sill Sealer To the Floor

Smear the caulk with your finger to make sure it adheres to both surfaces. Once the pour is complete, the sill sealer can easily be cut flush with a razor. The small void near the wall won’t negatively affect the tile installation.

6 / 17

Covering vents and drains with cardboard | Construction Pro Tips
FAMILY HANDYMAN

Install Cardboard Around Vents and Drains

Large holes, like heating vents and floor drains, can be isolated with cardboard before pouring your floor leveler. Just shape the cardboard to the hole, tape it in place, and then caulk it on the floor. The boxes that hold the flooring are often a convenient source of cardboard.

7 / 17

Building a dam in a doorway | Construction Pro Tips
FAMILY HANDYMAN

Build Dams in Doorways

Dam up doorways with strips of wood. Make sure you seal the wood to the floor with caulk as well as the area where the wood strip meets the sill sealer.

8 / 17

Priming the wood to seal the floor | Construction Pro Tips
FAMILY HANDYMAN

Prime the Wood

Wood floors need to be primed before covering them with self-leveler. The floor will be covered with water-saturated leveler, which will cause the wood to swell. It will shrink back down when it dries, which could cause cracks in the underlayment and tiles above. The primer prevents the wood from absorbing water. You can be roll, brush or even spray primer.

9 / 17

Tacking down the lath to the subfloor | Construction Pro Tips
FAMILY HANDYMAN

Install the Lathe

A lathe adds strength to the underlayment, like rebar adds strength to concrete. Avoid the metal lathe when working with in-floor heating. Check with the manufacturer of the heating system whether the lathe should be installed over or under the mat/cables.

  • Overlap the lathe at least three inches, and secure it with a tacker hammer stapler.
  • Keep the lathe 1-in. or so away from the walls so it doesn’t poke through the sill sealer when installing it.
  • Try to keep the lathe as flat as possible so it doesn’t rise higher than the depth of your pour.
  • Always check the continuity of the heating cables or mats before you start mixing. If you accidentally sever or nick a cable, it’s a lot easier to repair it before the underlayment is poured.
10 / 17

A stack of bagged self-leveler | Construction Pro Tips
FAMILY HANDYMAN

Order More Floor Leveler Than You Need

Running out of leveler before a pour is finished is kind of a big deal… so don’t do it! Buy 20 percent more floor leveler than you think you need. A large room poured even 1/16-in. thicker than anticipated can gobble up several additional bags of floor leveling compound.

Also, bags of leveler can be ruined by absorbing moisture from the ground. Keep your bags dry by setting them on a pallet or a sheet of plywood resting on scrap 2x4s, the same way you would protect bags of concrete mix.

11 / 17

Filling the mixer bucket with a hose | Construction Pro Tips
FAMILY HANDYMAN

Fill the Mixer Bucket

Keep a bucket on hand to place the mixer in when you’re not using it. Fill the bucket 3/4 full of water. That way, the floor leveling compound won’t stick to the paddle, and the bucket won’t tip over when you stick the heavy mixer in it.

12 / 17

Open a corner of the bags before you need them | Construction Pro Tips
FAMILY HANDYMAN

Prep the Floor Leveler Bags

Most bags filled with dry cementitious mixes have a vent in the top. It’s there so the bags don’t bust open when they’re handled. Minimize the mess produced by floor leveling compound by keeping the vent side up. Line the open bags up next to the buckets.

Mixing is a messy business, so do it outdoors whenever possible. Extreme temperatures can affect the time it takes the leveler to set up, so never mix up a super cold leveler or work in the blistering hot sun.

13 / 17

A bucket with two holes in it | Construction Pro Tips
FAMILY HANDYMAN

Make a Fill Bucket

Make a bucket that can be filled quickly. Fill a clear bucket with the proper amount of water and draw a fill line with a marker on the outside of the bucket. Another option is to drill holes at the fill line so the bucket will drain to the proper level. Dipping a bucket into a barrel filled with water is a lot faster than filling it with a garden hose over and over again.

14 / 17

Three buckets all in a line for easy mixing | Construction Pro Tips
FAMILY HANDYMAN

Mix a Bunch of Self-Leveling Underlayment at Once

Fill all the buckets with the recommended amount of water before you start mixing. Keep the buckets close to each other to reduce the mess when moving the mixer from one bucket to another. Keep all of the bucket handles facing out so they’re easier to grab (every second counts).

Once you’ve mixed all the buckets of floor leveler, go back to the first and mix it up again for a few seconds in order to stir up the sand that settled. Pull the mixer out and set it in the next bucket to be hauled in. After dumping each bucket, fluff up the sand in the next one before hauling it in.

15 / 17

FAMILY HANDYMAN

Spread as You Pour

Move the bucket along the floor as you pour. Keep the bucket low to minimize splashing. If you do splash on the wall, try to resist the temptation of wiping it off right away because small drops can quickly become large smudges. You’ll have better luck letting it dry and scraping it off.

Completely cover the heating cables/mats with floor leveler to avoid damaging them with a trowel while installing the thin set. The thickness of your pour may vary depending on your project, but shoot for a thickness between 1/2 in. and 3/4 in. Anything over 3/4 in. will likely require two pours, but confirm that by reading the instructions printed on the bag of the product you’re using. Check the thickness with a gauge rake, a junky tape measure or just a Popsicle stick with the desired thickness marked on it.

Move Floor Leveler With a Gauge Rake

A gauge rake is a metal squeegee that rides on two adjustable depth guides. This tool isn’t absolutely necessary, but it does work well at spreading the leveler around, and it helps to “gauge” how thick the self-leveler is. Be careful to work the rake very gently near the heating cables or mat.

16 / 17

Start pouring at the edges and work out | Construction Pro Tips
FAMILY HANDYMAN

Pour Your Way Out

Start at the far end of the room and work your way to the door. If you pass other entry points along the way, make sure to lock the doors and hang “keep out” signs so no one gets stuck in the floor leveling compound.

17 / 17

Washing buckets right away | Construction Pro Tips
FAMILY HANDYMAN

Wash Buckets Right Away

Wash your buckets as soon as you’re done pouring the floor leveler, and never dump the dirty water down a drain.

FAQ

How long does it take to dry?

Check the drying time on the product you purchase. Many self-levelers are walkable within 4 to 6 hours and ready for tile or flooring after 16 to 24 hours, says Nytes, but some fast-setting versions cure in just a few hours.

What causes self-leveling underlayment to crack?

Many factors contribute to cracking, according to Zimmerman. They include:

  • Poor bonding with the substrate;
  • Movement of the substrate;
  • Existing cracks in the substrate;
  • Rapid drying caused by exposure to sunlight, extreme heat, cold or humidity;
  • A mixture that’s too dry;
  • Overly thick applications.

To reduce the possibility of cracking, she advises ensuring thorough substrate cleaning and preparation and following the manufacturer’s guidelines for mixing, application, and curing.

About the Experts